University topic explanations and practice

University › Science and Engineering › Electric Power System Analysis

Electric Power System Analysis · Grid Layers · 256

Distinguish the layers of the power grid and explain the voltage range and main function of each. Reliability and protection in radial, ring and mesh topologies.

Free panel

Learning Outcomes

Topic Explanation

Function and layers of the grid

The electricity grid is the totality of the physical and control layers that deliver the energy generated at production points to consumers. This whole does not consist only of wires and poles; it includes numerous components that perform voltage conversion, switching, metering, protection, and communication functions. In the layered approach, the system is divided into the stages of generation, high-voltage transmission, intermediate-voltage connection, medium-voltage distribution, and low-voltage consumption. Each level has its own voltage range, line length, and power capacity. This distinction is not random: if energy is transmitted over long distances at high voltage, the current decreases and conductor loss is reduced; as the point of consumption is approached, the voltage is gradually reduced. Transitions between layers are provided by transformers, and the ratio of voltage to current changes at each transition while power is maintained.

For the grid planner, the layers also represent different scales of analysis. In the transmission layer, load changes in the order of minutes and hours, line openings, and generation losses are priorities. In the distribution layer, individual consumer behaviors that change within seconds, phase unbalance, and voltage fluctuations are decisive. Therefore, the same grid is represented by different models depending on the layer being examined. While lines are generally modeled with series impedance and shunt capacitance in transmission, line resistance becomes more dominant in distribution. Drawing the boundary between layers correctly ensures that calculations are both accurate and manageable. An incorrect boundary results in unnecessary detail or the oversight of a critical effect.

Generation and transmission interface

Generation units are usually connected to the grid at medium voltage and stepped up to transmission level by a step-up transformer. The purpose of this transition is not only to increase the voltage, but also to limit the fault current of the generating unit and to bring the impedance between it and the grid to the appropriate value. The generator's own impedance, the transformer's leakage impedance, and the impedance of the connection line together form a series resistance; This sum directly determines the magnitude of the current at the time of the fault. The voltage at the connection point indicates whether the generated power can be supplied to the grid without any problems. Therefore, modeling the generation interface is equally important for both normal operation and fault analysis.

The transmission line acts like an impedance element that carries power between two stations. In long lines, in addition to the series impedance, the capacitance to ground and between phases must also be taken into account. Capacitance causes the voltage to rise at the end of the line under light load; under heavy load, the drop caused by the series impedance becomes dominant. The thermal capacity of the line determines the maximum permissible current, and when this limit is exceeded, conductor sagging or insulation aging occurs. The stability limit also comes into play at the transmission layer: active power transmission is limited to a certain value of the line angle. The smallest of these three limits determines the actual usable capacity of the line.

Voltage levels and division of duties

Voltage levels are the result of a combination of economic and technical preferences. High voltage reduces the conductor cross-section and losses because it carries the same power with a smaller current; however, the insulation cost, pole height, and substation area increase. Medium voltage is a flexible intermediate solution for urban distribution; the balance between supply distance and load density is established here. Low voltage, on the other hand, provides a safe connection to the end user. In the transition between levels, the transformer ratio matches the nominal voltages of the two sides, and the same ratio is maintained regardless of the direction of power flow. The choice of voltage level also affects the magnitude of the short-circuit current; the fault current tends to be higher at a transformation point fed from a higher level.

Each voltage level has its own unique protection and measurement approach. At high voltage, measurements are taken through current and voltage transformers, and protection relays process these intermediate voltage signals. At medium voltage, the single-phase ground fault current can be very small or large, depending on the grounding arrangement; this directly determines the sensitivity of the protection. In low voltage, touch voltage and residual current protection are priorities. Coordination between levels ensures that a fault only results in the shutdown of the affected section. If coordination is disrupted, a minor fault can cause the entire supply area to be lost.

Radial, ring and mesh topologies

In a radial topology, there is a single supply path to each load point. This arrangement is simple, inexpensive, and predictable in terms of protection; however, a fault in the supply line leaves all consumers at the end of the line without power. In a ring topology, the supply is bidirectional, and in the event of a fault, it is possible to supply the load from the other side. The price of this flexibility is that the protection settings need to be reconsidered when the direction of flow changes. In a mesh topology, there are multiple parallel paths; The power flow is automatically distributed according to the impedances, and the opening of a single line usually does not cause a serious outage. However, it becomes more difficult to predict the flow, and protection selectivity and load flow calculations become more complex.

The choice of topology is a trade-off between reliability and cost. In radial supply, the investment is low and the downtime is high; in mesh supply, the investment is high and operational flexibility increases. In distribution networks, a loop is often established, but in normal operation, the supply is provided from the open point of the loop. In the event of a fault, the open point is closed, and the load is transferred by opening another circuit breaker. This process is called feed switching and is carried out according to pre-calculated scenarios. After the load transfer, it should be checked whether the new line is overloaded, whether the voltage remains at the limit, and whether the protection settings are valid. Otherwise, there is a risk of a new fault occurring while the outage is being resolved.

Substations and busbars

The substation is the node where voltage transformation, switching, protection, and measurement functions converge. The busbars in the substation form the common connection point for the incoming and outgoing circuits. The single-busbar layout is economical, but may require all circuits to be disconnected during maintenance. In a double busbar arrangement, circuits can be connected to one of the two busbars; during maintenance, the load can be transferred to the other busbar without being interrupted. The order of the switching devices is also important: the load-break switch can interrupt the current but not the fault current, while the circuit breaker can handle both situations. The disconnector only provides a visible point of disconnection and should not be opened while carrying current. Locking these devices is an essential part of maintenance safety.

The capacity of a substation is not only measured by the power of the transformer; the busbar current, the breaking capacity of the circuit breaker, and the short-circuit withstand capability also impose limits. When transformers are operated in parallel, load sharing occurs according to impedances; if the impedances are different, one is loaded earlier. The substation's auxiliary service transformer supplies power to the protection and control circuits and is necessary for re-energization after an outage. The accuracy of the metering circuits is critical for both billing and protection decisions. The saturation of the current transformer can prevent the accurate measurement of the fault current and cause the protection relay to make an incorrect decision. For this reason, the metering class and the protection class are selected separately.

Feeder areas and load centers

The supply area is a geographical or electrical cluster of consumers supplied by a specific source. The boundaries of the zone are drawn taking into account the length of the lines and the voltage drop. The load center is the point where consumption is concentrated, and bringing the grid investment closer to this point reduces losses. The time profile of the load within the zone determines the maximum demand at the same time; If the peak values of consumers do not coincide at the same time, the diversity factor comes into play, and the total demand is less than the sum of the individual peak values. When calculated correctly, this effect reduces the need for investment. If it is miscalculated, either unnecessary capacity is installed or the voltage limit is exceeded during peak hours.

Zonal supply is also the primary means of limiting the spread of faults. If each section has its own circuit breaker and protection setting, the fault remains only in that section. When determining section boundaries, the fault current level is taken into account as well as the load density. Since the fault current is high in areas close to the upper level, the breaking capacity of the circuit breaker should be greater. When a new load center is added, it is not enough to simply run a line to that point; The capacity, voltage profile and protection coordination of the existing line should be reviewed. Otherwise, the new load creates an invisible weak point and manifests itself under the first severe condition.

Modeling and mapping of grid elements

Grid analysis begins with the establishment of a mathematical representation of the physical facility. Each line, transformer, generation unit and load is represented by elements called nodes and branches. The voltage magnitude and angle at the nodes and the current and power at the branches are unknown. The accuracy of the model depends on the quality of the data to be used; the line length, conductor type, transformer leakage impedance and load values must be exactly the same. Incomplete or incorrect data quickly renders the calculation meaningless. Therefore, model verification is performed using field measurements, and the calculated stress is compared with the measured stress. If consistency cannot be achieved, the data is questioned first, not the result.

Mapping establishes the link between the model and geographical reality. Information about which poles a line passes through, which regions it supplies, and what the backup supply routes are enables quick decision-making in fault management. Teams working on the digital map visually monitor the locations of circuit breakers and load transfer scenarios. Every change made to the model must be recorded on the map and in the field records; Otherwise, after a few months, it becomes unclear which record is correct. As the network grows, this record-keeping discipline becomes a factor that determines operational speed as well as computational accuracy.

Key Points

Worked Examples

Worked Example

Worked Example

Worked Example

Worked Example

Worked Example

Common Mistakes

Tips

Practice Questions

  1. 1. At what voltage level is energy transmitted over long distances in the layered structure of an electrical grid?
  2. 2. In the layered grid approach, which device is used to reduce voltage?
  3. 3. Which of the following is the most distinctive feature of a radial topology?
  4. 4. In a ring topology, by which process is the load supplied from the other side after a fault?
  5. 5. Which of the following is the basic parameter that determines the distribution of power flow in a mesh topology?
  6. 6. Which of the following is limited by the thermal capacity of the transmission line?
  7. 7. Which of the following effects causes voltage rise at light load on a long transmission line?
  8. 8. Which of the following is the parameter that determines the load sharing when the transformer operates in parallel?
  9. 9. Which of the following is the most significant drawback of a single-busbar substation?
  10. 10. Which of the following is a switching device that should not be opened while under current?
  11. 11. Which of the following is the main difference between a circuit breaker and a load-break switch?
  12. 12. What can be the result of the saturation of the current transformer?
  13. 13. Which of the following is the reason for separating the billing metering and protection metering classes?
  14. 14. Which of the following is the main benefit of bringing the load center closer to the consumer?
  15. 15. In which situation does the diversity factor reduce the total load?
  16. 16. Which of the following should be checked when a new center of gravity is added?
  17. VOLUME 17 In the network model, which of the following do the concepts of node and branch represent?
  18. 18. Which of the following is the first thing to do when the model and the field measurement do not match?
  19. 19. Why is it important to maintain the match between the network map and the model?
  20. 20. How does the current change when the same power is carried at a higher voltage?
  21. 21. What trend emerges when the cost of insulation increases in the selection of voltage level?
  22. 22. Which of the following is a result of high-voltage transmission?
  23. 23. Which topology is most affected when a feeder line in an area is switched on?
  24. 24. Which of the following is the main function of the auxiliary service transformer in the substation?
  25. 25. How does the angle required for the same power transfer change when the series impedance between two nodes increases?
  26. 26 Which of the following is not taken into account when drawing the boundaries of the catchment area?
  27. 27 Which of the following quantities is preserved during voltage transformation?
  28. 28 What happens in the event of a fault if the breaking capacity of the circuit breaker is underspecified?
  29. 29 Which of the following is the risk that arises when the busbar current limit is exceeded?
  30. 30 What is usually the result of opening a single line in a mesh network?
  31. 31 Which of the following is the reason why the ring network is operated with an open point during normal operation?
  32. 32 Which of the following is the most reliable comparison used to validate the grid model?
  33. 33 By which relation is the impedance base calculated?
  34. 34 Which of the following is a typical characteristic of the distribution layer?
  35. 35 Why is load forecasting necessary in grid planning?
  36. 36 Which of the following factors limits the fault current when a generation unit is connected to the grid?
  37. 37 Which of the following is the correct order of the network layers?
  38. 38 In which of the following situations can a load switch be used?
  39. 39 How does the power transmitted for the same current change when the voltage level of a line is increased?
  40. 40 What risk does failure to keep network records up to date pose?
  41. 41 Which of the following checks should be carried out after changing the feed?
  42. 42 Which of the following quantities is resolved as unknown at a node?
  43. 43 Which choice is made more difficult by the increased cost of insulation on high-voltage lines?

Source: Inspired by open curricula of Turkish universities; the explanation is written originally.

Kaynak: Türkiye üniversitelerinin açık ders planlarından esinlenilmiştir; anlatım özgün olarak yazılmıştır.